Quote:
Originally Posted by jaguarbob View Post
no,...just the finishing of the exterior and interior block walls ready for paint,and the floors of course are cemented and will be tiled someday in the future.It does include the locations of the pipes and the electrical tubing has been pulled thru some walls.The pipes for water and septic tank have been bought but not installed fully yet,and of course I still have to put in the septic,which will take some more rocks and labor but will do that after the roof is installed.
I just posted this as info on a Dominican house,not one done by developers,builders,etc.This is how most houses are built by the average 6000 peso a month Dominican.
You can see how much profit there is here on these houses built and sold by developers.
bob
finally got money saved up for cement roof...total cost was 100,000 pesos,which included 100 bags of cement,at 250 pesos a bag,6 loads of dirt at 1500 pesos a load,and 6 loads of rock at 2300 pesos a load.Rental of wood was about 8000 pesos,and pipe,etc was not much.I had already bought the barrila for about 45000 pesos last year.House is 35 by 35 feet.
and of course the man doing the roof was paid and a few workers to do labor was mostly family.

now I need to do elec,plumbing,finish the walls,etc,but the roof was a very important piece for me as the other work can be done as i can....little at a time.

bob